Check that the issued construction drawing is the latest revision.
Kerbs 1. Engineer to set out Kerb lines, gully and manhole positions. 2. Kerb pans to be set up and concreted in accordance with the design spec. 3. String lines to be tied to the kerb pins at the required height and a visual check carried out. 4. Kerbs to be laid out prior to laying. 5. A mechanical kerb lifter should be used, if not manual handling techniques to be used by the kerb layers. 6. Kerbs to be haunched in accordance with the design spec.
Manholes & Gullies 1. Manholes to be excavated and constructed in accordance with the design specification. Engineer to set out lines/pipe laser. 2. Gully pots are to be installed with a string line established on the kerb line to ensure correct position and height. 3. Pipelines to be air tested prior to backfilling. 4. Backfilling in accordance with the specification. 5. Brick work to gullies and manholes in accordance with the design spec, the Site Engineer to set out and check manhole and gully cover levels. 6. Ducts to be installed and draw ropes to be tied off.
|
-
Categories
- COSHH (7)
- Health and Safety (76)
- Method Statements (70)
- Personal Protective Equipment (1)
- Risk Assessments (56)
-
Pages
-
Archives
- June 2020 (1)
- January 2020 (1)
- November 2019 (1)
- August 2019 (1)
- April 2019 (1)
- March 2019 (1)
- February 2019 (1)
- January 2019 (4)
- September 2018 (1)
- July 2018 (2)
- April 2018 (1)
- December 2016 (1)
-
Blogroll
-
Meta
Basic Method Statement Kerbs and Gully Construction
Posted By safetyadmin On Thursday, August 4, 2016 07:59 AM. Under Method Statements
Tags: kerbs and gullies
Comments are closed.